The first-stage no-load trial operation of Zhengzhou Metro Line 3 has end its 91-day running and it is about to put into the initial operation.
记者昨日获悉,为期91天的郑州市轨道交通3号线一期空载试运行正式结束,3号线即将投入初期运营。
The first stage of Metro Line 3 will start no-load trial operation from September 8, and will be divided into three stages. The first phase (September 8 to October 7)has completed the verification of system functions and the applicability of system standards. The second stage ( October 8 to November 6)has completed the system linkage function test and drill; The third stage (November 7 to December 7)has organized the trial operation of "running chart".
3号线一期工程于9月8日起空载试运行,共分3个阶段,其中第一阶段(9月8日~10月7日),完成系统功能及制度标准适用性核验;第二阶段(10月8日~11月6日),完成系统联动功能测试及演练;第三阶段(11月7日~12月7日),组织试运行“跑图”。
By December 7, the first stage of Line 3 had been running for 91 days, and the main line had been running about 222,762 kilometers.
截至12月7日,3号线一期工程已安全行驶91天,正线安全运行约22.2762万列公里。
After the trial operation, the first phase of Line 3 will carry out the final safety test and system debugging of the train, and the train will be operated in the early stage of society after passing the safety review.
试运行结束后,3号线一期工程将对列车进行最后的安全检测、系统调试,待安全评审通过后面向社会初期运营。(记者 张倩 通讯员 周静雯 文/图)